Scenario: A 10 MW Solar Plant

  • Installed capacity: 10 MW
  • Annual generation: ~17,000 MWh (1,700 h/yr capacity factor)
  • Linked consumption sites: 8 factories/branches monitored via Etta
  • Average MCP: 2,400 TRY/MWh, peak deviation: ±40%

The Real Annual Cost of Manual Tracking

Loss ItemAmountAnnual Cost
Hour-matching errors (3-5%)~510 MWh1,224,000 TRY
MCP/YEKDEM misapplication~2% drift816,000 TRY
00:00-02:00 timezone shift (Excel)~120 MWh288,000 TRY
Manpower (1 full-time analyst)—600,000 TRY
Missed consumption peaks (no Etta)~4% extra bill480,000 TRY
TOTAL ANNUAL LOSS~3,408,000 TRY

Most of this loss is invisible — it's not money lost, it's money never earned.

Automated Management with SmartPlain + Etta

SmartPlain — Generation Side

  • Automatic hourly matching of generation, MCP, YEKDEM and KBK multipliers
  • Europe/Istanbul timezone standard — zero shift between 00:00-02:00
  • Real-time market data via EPİAŞ integration

Etta — Consumption Side

  • Hourly OSOS data from YEDAŞ / AYEDAŞ / OSMANGAZİ
  • Real-time peak alerts and penalty-hour detection
  • Multi-site (8 factories) management from one panel

Two-Way Balancing

Surplus hours route to consumption sites; deficit hours trigger SmartBe spot-market optimization. The consumption_site_id link binds plant ↔ factory in one click.

Annual Gains with SmartPlain + Etta

Gain ItemImprovementAnnual Gain
Hour-matching accuracy99.7%+1,180,000 TRY
Tax/YEKDEM automationfull accuracy+800,000 TRY
Timezone shiftszero+288,000 TRY
Analyst workload → 1 hr/week review—+550,000 TRY
Etta peak alerts → load shifting4% → ~0.5%+420,000 TRY
TOTAL ANNUAL GAIN~3,238,000 TRY

Net ROI: After SmartPlain + Etta licensing, the investment pays back in under 2 months.

Balanced SmartPlain ↔ Etta Scenarios

Scenario 1 — Midday Generation Peak (12:00-14:00)

Plant runs at full capacity while Etta detects rising cooling load. The system suggests: "Start the 800 kW cooling unit at Factory 3 now — direct match to generation."

Scenario 2 — Evening Consumption Peak (19:00-22:00)

Generation has dropped to zero, Etta shows a sharp consumption rise. SmartBe issues a "Buy 4 MWh from spot now" signal before MCP rises further.

Who Needs This?

  • Solar plant owners ≥ 5 MW
  • OSB members with multiple sites
  • Chains/groups managing generation and consumption separately
  • Hybrid (PV + battery) operations

Conclusion

The annual gap is ~3M TRY at 10 MW, and even ~300K TRY at 1 MW. Manual tracking isn't cheap — it's just invisibly expensive. SmartPlain + Etta collapse that invisibility into one dashboard.

Want this calculation for your own plant? Request a demo via the contact form.


Disclaimer: Calculations assume 10 MW installed capacity, 1,700 h/yr capacity factor and 2,400 TRY/MWh average MCP. Real values vary by site, contract type, consumption profile and market conditions.